Pleasant Park: what the record says about its purpose and its one way in

Pleasant Park was planned as both a home for local field programs and a tournament venue, and its single entrance was flagged before it was designed. Here is the record, year by year, and where the access study stood after its Nov. 10 update to Council.

Aerial view of Pleasant Park's playground, shelters and turf fields
Pleasant Park. Photo: Town of Apex
92 acresbought by Council in October 2014
Dec. 2015first record of the single-access concern, from the Town's design consultant
8,000–10,000visitors a day in the first week after the Nov. 4, 2023 opening
Up to 5new access points in the $150,000 CAMPO study approved Mar. 10, 2026

Two questions

What the record actually says

Claims have circulated about why the park was built and when the access problem first came up. Pick a question to see the dated documents.

Both: local fields and tournaments, from the start

Every planning document from 2013 to the 2017 bond names two goals: meet Apex's own field needs and host tournaments.

2013

The parks master plan's long-term needs include a 60–100 acre sports complex that can “not only meet active recreation needs, but also serve as an economic tournament venue for the town.”

Parks, Recreation, Greenways & Open Space Master Plan, 2013 (p. 9)Master plan (PDF) ↗
2014

Council approved buying the 92.16-acre Progressive Farms property, 5–0. Staff said it met the master plan's goal of significant parkland in the southwest quadrant and addressed current and future program needs.

Approved minutes, Oct. 21, 20142014 minutes (PDF, p. 172) ↗
2017

Before the bond vote, the Town's Pleasant Park page described both: fields that expand softball, baseball, tennis, soccer and lacrosse programs, and a tournament facility, “allowing Apex athletes to stay and play.”

Town of Apex Pleasant Park page, July 2017Archived copy ↗

The place

Between the railroad and NC 540

The park sits south of Old US 1 and the CSX line, with NC 540 on its east side. Its single entrance crosses the rail corridor. The access study's own map shows the options it is weighing, including a crossing just north of the park toward S. Salem Street and one across NC 540.

Marker locations are approximate. Map data © OpenStreetMap contributors.

Pleasant Park Access Study: Planned Roadway Network (Town of Apex / CAMPO, Aug. 2026)Study map (PDF) ↗

Opening and after

From opening day to the access study

  1. 1

    Nov. 4, 2023

    The park opens with one way in

    In its first week, the park averaged 8,000 to 10,000 people a day, the interim Town Manager told Council.

    Approved minutes, Nov. 14, 20232023 minutes (PDF, p. 848) ↗
  2. 2

    June 17, 2025 · Council work session

    “Getting a second access point is number one”

    As Council chose a design for the park's second phase, Councilmember Terry Mahaffey said access was his primary concern: of two issues, “parking is number two and getting a second access point is number one.”

    Approved minutes, June 17, 20252025 minutes (PDF, p. 538) ↗
  3. 3

    Mar. 10, 2026 · Council meeting

    Council approves the access study, 5–0

    On Mayor Pro Tem Mahaffey's motion, Council approved the consent agenda, including an interlocal agreement with CAMPO, the region's transportation planning organization, to study up to five potential multimodal access points. The study costs $150,000, split evenly between the Town and CAMPO; the consultant is VHB.

    Approved minutes, Mar. 10, 2026 (CN1)2026 minutes (PDF, p. 192) ↗
  4. 4

    Nov. 10, 2026 · Council meeting, item PR5

    The study team reports back

    Town planning staff and VHB, the study's consultant, presented the first round of public input. Six performance measures will score each option: cost and funding, constructibility, connectivity, neighborhood impacts, operations and environmental impacts. At the Sept. 3 public meeting, residents ranked neighborhood impacts most important, followed by connectivity and operations, and those rankings will help weight the scoring. The team said its 10% concept designs were being finalized to feed cost estimates. The item was informational; no option was chosen.

    Pleasant Park Access Study update, Town Council, Nov. 10, 2026 (from 1:27:31). Video: Town of Apex
    Council agenda item PR5, Nov. 10, 2026 (packet p. 508)PR5 coversheet (PDF) ↗

Where it stands

The study, step by step

The study will evaluate up to five potential new access points and recommend one for future funding. It is a feasibility study: funding has not been identified for design or construction.

  • ✓
    Existing conditions analysis & public meeting #1Sept. 3, 2026, Apex Town Hall
  • ✓
    Performance measures set; update to Planning Board and Town CouncilNov. 9 and Nov. 10, 2026
  • →
    10% concept designs, cost estimates & scoringBeing finalized at the time of the Nov. 10 presentation
  • 4
    Public meeting #2Jan. 27, 2027
  • 5
    Draft study reportExpected March 2027
  • 6
    Final report and recommended access pointStudy wraps up May 2027
apexnc.org, Feasibility Studies (captured Nov. 11, 2026)apexnc.org/1851 ↗
Project website (captured Oct. 7, 2026)publicinput.com/n58787 ↗

How to weigh in

Second public meeting: Jan. 27, 2027

The study team will show concept designs at the second public meeting on Jan. 27, 2027. Residents can follow the study, sign up for updates and comment on the project website. The Town posts status updates on its Feasibility Studies page.