S. Salem Street by bike, block by block

Apex is designing a bike connection from Pleasant Park to downtown. It would not be one thing from end to end: some blocks get lanes, one stretch gets a path, and the last blocks share the road. Here is the plan, segment by segment, and how to tell the Town what you think.

Town rendering of S. Salem Street on the bridge over NC 540 with buffered bike lanes on both sides and people riding
Segment A on the NC 540 bridge, from the Town's open house boards. The raised sidewalk is shown for future reference and is not part of this project. Rendering: Town of Apex / McAdams.
2.9 mifrom Pleasant Plains Road, beside Pleasant Park, to W. Chatham Street downtown, in seven segments
2.0 miwould have a bike lane or path. The other 0.9 mile, into downtown, stays shared with cars
No. 2on the top 10 project list in Bike Apex, the Town's bicycle plan
Dec. 3open house, 4 to 6 p.m., Town Hall, third floor. The online survey runs through Dec. 16

Ride it

Seven segments, five treatments

Pick a segment on the strip or the map, then drag across the photo to compare today with the Town's preliminary design.

← Pleasant ParkDowntown →

Photos and renderings: Town of Apex / McAdams, open house boards (PDF). Lengths are approximate, measured by Peak News Network along the street.

Town of Apex: open house boards, segment mapPDF ↗

How much room riders get

Most room at the park end, least downtown

  • Off-road path one way, lane the otherC + D: 8- to 10-ft path southbound, 6-ft lane northbound0.45 mi
  • Buffered bike lanesA: 5-ft lanes with a 2-ft buffer0.70 mi
  • Striped bike lanesB: 6-ft lanes both sides, already there0.85 mi
  • Shared lane markings and signsG: "sharrows" painted in the travel lane0.29 mi
  • SignsE + F: bike signs, no lanes or markings shown0.63 mi

Why the change partway? Space. The Town says the mix comes from coordinating with the North Carolina Department of Transportation (NCDOT) while considering "the various constraints and street sections along the corridor." The Bike Apex plan, adopted in January 2019, said the same about the last stretch: from downtown to the Peakway the street is too tight for bike lanes. Residents wanted the route anyway: the plan lists it first among the routes they mentioned most, "by far," when the Town showed them the draft network.

Town of Apex: Bike Apex plan, Priority Project 2 (p. 67)PDF ↗
Town of Apex: Bike Apex plan, top 10 projects (p. 5)PDF ↗

Why this road

Segment B already has bike lanes. The segments on either side do not. When Town Council discussed S. Salem in October 2023, one Councilmember said striping there would be left without a connection. The transportation director explained that S. Salem is a state road, and that the state typically does not like marking roads unless there are connections. This project is the connection: A reaches the park, C and D carry riders past the new Peakway bridge, and E, F and G finish the route downtown.

Town of Apex: approved Council minutes, Oct. 10, 2023PDF ↗

Segment D passes under the new Apex Peakway bridge, where crews have been rebuilding the road. At the Oct. 27, 2026 Council meeting, the Peakway update reported asphalt paving along S. Salem in progress. The S. Salem project is also on the Town's map of what surrounds the planned Tingen Road crossing, a walking and biking route meant to replace the railroad crossing that has to close when the Peakway bridge opens.

Town Council, Oct. 27, 2026: the Peakway update, including paving along S. Salem. Video: Town of Apex.
Town Council, Aug. 12, 2025: staff list what would connect at Tingen Road and S. Salem. Video: Town of Apex.

What changes for you

On a bike, behind the wheel, on foot

N.C. General Statutes: G.S. 20-150(e), passing a bicyclencleg.gov ↗

On the record

Bike lanes "when they re-pave"

In 2023, Mayor Pro Tem Terry Mahaffey, then a Councilmember, pressed for a quicker way to build out the bike network. On Oct. 10 of that year he seconded the motion that added bike lanes on major collector streets to the Town's Bicycle and Pedestrian System Plan Map. It passed 5–0. In the discussion, the minutes say, he told staff it should always be the Town's policy to do bike lanes when they re-pave, and that he wanted a budget to find busy streets and re-stripe them early. When staff said funding would be the next step, he said he would give it to them through Council. He also said any physical separation from traffic was good.

Town of Apex: approved Council minutes, Oct. 10, 2023PDF ↗
Town of Apex: approved Council minutes, Oct. 10, 2023PDF ↗

He questioned the price of the S. Salem project that night, too, since some bike lanes are just re-striping. Staff's answer: this one would need widening, and the railroad beside the road complicates it. In September 2026 he flagged the Dec. 3 meeting in his newsletter, writing of this and other road projects: "I encourage residents to review plans early and participate when meeting details are confirmed."

Terry Mahaffey: Apex Update: Planning for the Future, September 2026Newsletter ↗

Money and schedule

Funded through right-of-way, not yet construction

Federal$850,000in federal earmark money, with a $212,500 match from the Town
FY2025–26 capital plan$3.18Mover two years: $1.06 million with the federal money, then $2.12 million from the Town
Latest estimate$4.6Min the Town's October 30, 2026 status report

The survey page says it plainly: the project is in preliminary design and funded through the right-of-way phase, and "additional funding would be needed to construct this project." The current capital plan (FY2026–27) lists the $2.12 million for FY2027–28. A capital plan is a plan, not an appropriation; each year's budget decides. In August 2025 Council voted 5–0, on consent, for the review and oversight agreement with NCDOT.

Town of Apex: S. Salem Street Bicycle Connection surveypublicinput.com ↗
Town of Apex: Capital Transportation Projects Status Report, Oct. 30, 2026, p. 7Project page ↗
Town of Apex: FY2025–26 budget, capital plan funding table (PDF p. 311)PDF ↗

The Town's schedule

Spring/summer 2026Data, field surveys, coordination
Fall 2026Options and community engagement
Winter 2026 to summer 2028Design and right-of-way
Winter 2028Anticipated start of construction
Town of Apex: open house flyerPDF ↗

Your say

Two ways to weigh in

Thursday, Dec. 3Open house, 4 to 6 p.m.
Apex Town Hall, 73 Hunter Street, third floor. See the boards and talk with staff.
Through Dec. 16Online survey: a few multiple-choice questions and a comment box for each part of the route.
Take the Town's survey ↗

Draft your comment here, then paste it into the survey or bring it on Dec. 3. Nothing you pick or type leaves this page.

I use S. Salem Street to…
The segments I use
I'd like the design to consider…
Open the survey ↗

Questions go to the Town's Traffic Engineering Manager, Russell Dalton: russell.dalton@apexnc.org or 919-249-3358.

Town of Apex: Pedestrian, Bike, and Transit Projectsapexnc.org/1848 ↗

Bottom line

The design is still open

Residents asked for this route when they helped write the bike plan, and the Town now has a design to show them. Two of its nearly three miles would give riders their own space. The last stretch into downtown, where the street is tightest, is where local knowledge can help most, and the Town is asking for it now, while the plan is still preliminary.