All articles

Downtown · History

Trees for Salem Street: 1966 to 2026

Apex's 1966 downtown plan found trees were rare and asked to bring them back to Salem Street. A 1976 plan asked again, the 1993–96 rebuild left them out, and the streetscape being built this year includes them.

N. Salem Street in downtown Apex in 2025: two-story storefronts with awnings, crosswalk, parked cars and traffic signals strung overhead
N. Salem Street, 2025, before the current construction began. Photo: Pithon314 / Wikimedia Commons (CC0)

Downtown Apex has been planned and replanned for six decades. In September 1966, the Town's C.B.D. Improvement Plan, prepared with the N.C. Division of Community Planning, set out a staged program for Salem Street. Its first stage started with trees. Three decades later, the Town rebuilt the street, and the trees were left out again.

Apex's 2023 sesquicentennial history describes a downtown that had fallen on hard times by the late twentieth century, and presents the beautification work that followed as an effort to revive it. The 1990s project is often remembered as “1996,” but the Town's approved minutes show the steps stretched from late 1993 through 1996, with trees and parking still being discussed in 1997.

The stories below are drawn from those minutes, each shown as a scanned excerpt. They cover what was decided and what it cost where the record says, and they leave a gap where the record does not.

1966Apex's downtown improvement plan finds trees are rare and calls for trees along Salem Street
$2,250Dec. 21, 1993: first money set aside to study downtown streets and sidewalks
4–1Jan. 18, 1994: the Board adopts design “Scheme 6”
May 1996The Town announces a preservation award for the Salem Street improvements
Mid-Dec. 2026Substantial completion expected for today's Salem Streetscape, with street trees (Town, Nov. 6)

1966 to 1976

The first plan to bring the trees back

The 1966 plan was, in its own words, the result of a year-long effort by the Apex Planning Board, the Chamber of Commerce, the Downtown Improvement Association and other local groups. It found downtown short of parking and congested, and it noticed what was missing: trees had been uprooted years earlier to make room for progress and growth.

C.B.D. Improvement Plan, Apex, September 1966Plan scan ↗

Its first stage called for a merchants’ Downtown Improvement Association, textured sidewalks, coordinated storefront colors with voluntary sign control, new street furniture, and trees spaced along Salem Street between Chatham and Center streets.

C.B.D. Improvement Plan, Apex, September 1966: Stage OnePlan scan ↗
1966 sketch of a proposed tree-lined Salem Street with pedestrians, storefront canopies and parked cars
The 1966 plan’s sketch of a tree-lined Salem Street. C.B.D. Improvement Plan, Apex (NC State Library, public domain)

Much of that first stage happened. A 1969 community appearance study for Apex reported that unnecessary signs had come down, storefronts had been renovated with new color schemes, and a unified canopy plan covered much of downtown, including the Town Hall.

Community Appearance Study, Apex, 1969Study scan ↗

The trees waited. Apex’s 1976 Policies Plan noted that through traffic now went around downtown and saw an opportunity to plant seedling trees “for the future citizens of Apex.”

Policies Plan, Apex, 1976Plan scan ↗

Walk the record

Eight moments from the minutes

Pick a date to see what the Board recorded. Tap an excerpt to enlarge it.

    Dec. 21, 1993

    A $2,250 study

    The Board of Commissioners allocated $2,250 for a consultant to study the first phase of downtown streets and sidewalks. It is the first specific design authorization found in the minutes.

    Approved Board minutes, Dec. 21, 19931993 minutes ↗

    Try it

    The money came in pieces

    Check the boxes to add up the dollar figures in the minutes, and see why the record does not support a single total.

    $0

    Pick one or more.

    The minutes do not say whether the $25,000 is part of the $82,000, and the $110,000 covers paving, not necessarily sidewalks, lights, electrical work or design. Separate items, such as a $259,000 contract for a North Salem water-main extension, funded from unused water-bond money, may or may not overlap with the downtown work. The full authorized and final cost remains unresolved in the records reviewed.

    Then and now

    Street trees: 1995 and 2026

    Asked for in 1966 and again in 1976, the trees came up once more in the 1990s rebuild.

    • Aug. 1, 1995: the Board's consensus was that trees not be part of the project.
    • Sept. 19, 1995: a motion to leave room for six to ten street trees failed, 3–2.
    • 1997: merchants proposed 15 potted trees and asked the Town to share the cost; the Board referred it to the Planning Committee.

    Side by side

    1993–96 and 2026

    1993–962026
    DesignConsultant study (Dec. 1993), then Scheme 6 adopted by a 4–1 vote (Jan. 1994)Downtown Master Plan and Parking Study adopted in 2019; project design shared in a public meeting in Dec. 2022 (Town capital report)
    What's builtResurfacing, curb and gutter, sidewalks and brick paving; the Town's history also cites buried power lines and antique-style lightsStaggered parallel parking, widened paver sidewalks, urban street trees, decorative light poles, string lighting, planter boxes, wayfinding and street furniture, plus a Saunders Gathering Space (Town)
    Street treesLeft out in 1995; potted trees requested in 1997Part of the design, over underground soil cells
    TrafficThrough-truck restriction effective Nov. 1, 1995One side of the street closed at a time with an NC 55–Hunter Street detour; all businesses open (Town)
    ScheduleStart announced for May 1994; paving window May–Aug. 1995; award May 1996. Actual start and finish dates were not recoveredConstruction began Jan. 2026; substantial completion expected mid-Dec. 2026; final punch list mid-Jan. 2027 (Town)

    December 2025

    When the bids came in high

    Staff brought Council two options for the construction contract: award the low bid with a 10% contingency, or reject and rebid, possibly with a reduced scope, at the risk of missing the target of finishing before the next holiday season. Council chose to award.

    Council work session, Dec. 16, 2025: staff present the bids and the two options. Video: Town of Apex.

    Mayor Pro Tem Terry Mahaffey described the decision in his Dec. 17, 2025 newsletter. The low bid came in about $2 million over the engineer's estimate; the Town had rebid once and tried value engineering without finding obvious savings that would not greatly change the experience it wanted to deliver. Council weighed rejecting and rebidding, suspending the project, or pushing forward, and, he wrote, chose to push forward, unanimously.

    His reasoning, in his words:

    Terry Mahaffey, “Apex Fully Funds Downtown Streetscaping,” Dec. 17, 2025Newsletter ↗

    The same newsletter notes that the bid package required all stores to stay open and accessible throughout construction and capped the schedule at 270 days, to avoid affecting the fourth quarter of 2026, and that those protections added risk that drove up costs.

    What it adds up to

    Sixty years of asking for trees

    The 1966 plan asked to “recall” the trees to downtown, and the 1976 plan asked again. The 1990s record shows a project built in steps, with money from several sources, a debate over trees that the Board settled one way in 1995 and merchants kept raising, and a preservation award at the end. The 2026 project keeps the trees in the design, builds the soil underneath them, and, according to the Town, is on track for substantial completion in mid-December. All of it is still under construction, and delivery dates can move: check the Town's project page for the latest.

    Discussion

    Comments